1
Client : Lusail Real Estate Development Company
Contractor : QDVC 100%
Start date : July 2015
Finish date : May 2018

C3 Road of 550 lm

C2 Road of 450 lm

C1 A12 road of 1.6km

TRANSFER PACKAGES CP01 C1, C2, C3

QDVC has been awarded the CP01 Transfer Packages Project in Lusail City, covering three areas: C1, C2, and C3. The works include road construction and related services.

  • C1: About 1.6 km of road, plus the design and build of four 11kV substations and runs along the Marina, including the A12 road, intersections, and connecting roads to nearby plots.
  • C2: About 450 meters of road, located at the northern end of the Marina District, consisting of a single intersection.
  • C3: About 550 meters of road, situated in the southern Foxhill District.